Harbin Terrace Construction

Project Overview
A waterproofing and site improvement project is underway on the Harbin Terrace. The first phase of this project has been completed and all of the fencing has been removed. The terrace is now open and fully operational.
Impact
The additional phases of this project are expected to have minimal impacts. Community members can expect to see a construction fence on portions of the Harbin Terrace on and off until completion in August 2025. Additional impacts to Harbin residents will be communicated as needed.
Project Phases
The project is expected to be completed during Summer 2025 and spread out in several phases, outlined below.
Phase 1:
Completed
Phase 2
Completed
There will be continued waterproofing and structural repairs. In addition, there will be increased WiFi access and power outlets installed. Movable site furniture will be added.
Phase 3
Completed
In the third phase, we will install planted trays on the terrace to reduce the stormwater runoff, stormwater management measures in the area east of the pavement, and piping for an irrigation system. Lighting will be installed along with additional site furnishings. Impacts will be communicated forthcoming.
Site Improvements
- Synthetic turf on the terrace
- New outdoor furnishings including planters, modular seating, lighting and shade structures